Royal Group's 900MW Koh Kong LNG Plant Set to Begin Phased Power Supply in Late 2026
Royal Group's 900MW LNG power plant and special economic zone in Koh Kong are set to begin phased power supply from late 2026. The project is expected to bring jobs, industrial investment and a more stable national grid.
Royal Group's 900-megawatt (MW) liquefied natural gas (LNG) power plant and its accompanying special economic zone in Botum Sakor district are expected to give Koh Kong province's economy a real lift. H.E. Bou Chanphirou, Director General of the Insurance Regulator of Cambodia, made this assessment during a visit to the site to review progress. The project, worth more than $1 billion, is expected to bring jobs, draw industrial investment and open new opportunities for local suppliers.
Construction and timeline
Construction began in late 2024 in Thma Sa commune, Botum Sakor district. The plant is scheduled to start generating and supplying electricity in stages, from late 2026 through 2027.
Stronger energy security
Once it reaches full capacity, the 900MW facility should expand domestic power supply, reduce Cambodia's reliance on imported electricity and help meet rising demand. Because it can generate power around the clock, it will complement hydropower and solar and make the national grid more stable.
A new industrial hub
The special economic zone is being developed as a base for domestic and international investors in industry, manufacturing and related services. Combined with a large, reliable power supply, it is expected to attract new factories and investment, positioning Koh Kong as a destination for investors along Cambodia's coast.
Jobs and local opportunities
Building and operating the plant will require a wide range of workers, including electrical, mechanical and civil engineers, gas system technicians, welders, electricians, heavy machinery operators and construction crews. Administrative, accounting, warehouse, occupational safety and foreign-language interpretation roles will also be needed.
The influx of workers is also expected to boost demand for housing and rentals, restaurants, shops and transport in Botum Sakor and nearby areas, creating new income for local families. Roads, water supply, power lines and transport services built for the project will also serve surrounding communities.
How to apply
Job seekers should watch for recruitment announcements on Royal Group's official channels, those of its contractors, and the National Employment Agency. The companies involved will publish the number of positions, hiring dates and job requirements.