Cambodia to Build 120 km, 230kV Power Line Linking Solar Farm to National Grid
Cambodia plans a 120-kilometre, 230kV transmission line to bring solar power from Pursat into the national grid. The $183 million project aims to improve grid stability, cut outages and create jobs.
Cambodia is preparing to build a 120-kilometre high-voltage transmission line that will carry clean solar power to Kandal, Kampong Chhnang and Pursat provinces.
The 230-kilovolt line will be built by Electricité du Cambodge (EDC). The work also includes two new substations and upgrades to two existing ones. The project will be funded by a $183 million loan from the Asian Development Bank (ADB).
Minister of Mines and Energy Keo Rottanak announced the project on November 18. Its primary aim is to move electricity generated by the solar farms in Krakor district, Pursat province, into the national grid, where it can be distributed across the country. Those solar developments, under construction in Krakor, will have a combined capacity of more than 1,100 megawatts, which the minister called one of the largest green energy projects in the ASEAN region.
The project is expected to help Cambodia reach its goal of producing at least 70 per cent of its electricity from clean sources by 2030. Around 63 per cent of the country's power currently comes from clean sources such as hydropower, solar and biomass.
Three main goals
- A more stable grid: Rottanak said the network must keep growing to reduce power cuts in economic zones, industrial parks, farming areas and residential communities.
- Support for investment: A stronger power network would improve living standards and attract domestic and foreign investors as demand for electricity rises.
- Jobs and growth: The project is meant to boost economic activity and create employment. In Kampong Tralach district in Kampong Chhnang, more than 50,000 people already work in factories. With expanded power supply, that number could exceed 100,000 in the near future.
Rottanak said local job creation is also part of the government's effort to give young people work closer to home and reduce labour migration to distant areas.
He added that the electricity fed into the grid would benefit not only the three directly connected provinces but also other areas linked to the wider network, supporting tourism, agriculture and industry.
The minister thanked local authorities and residents for their support in getting the project underway. He urged them to keep working together until construction is complete so that local communities and the national economy can see the benefits.