Southeast Asia Needs to Tackle Early Financing Risk for Subsea Power Cables
The ASEAN Power Grid depends on subsea cables, but developers face heavy upfront costs to reserve scarce manufacturing capacity long before projects are financed. The authors argue that shared mechanisms are needed to spread this early-stage risk.
Interest from investors and the political will behind the ASEAN Power Grid (APG) are both strong. Still, sponsors, governments and financing partners must deal with the risks that arise at the earliest stage of a project. Without that, developers may not be able to lock in scarce cable-manufacturing capacity before conventional project finance becomes available.
Subsea power cables are becoming more important as economies grow more interconnected. They carry electricity across bodies of water, so power generated in one area can reach homes and businesses connected to another grid. More links also reduce dependence on a single source, such as hydropower, which can fall short during an El Niño-driven drought.
For Southeast Asia, undersea links sit at the heart of the APG, the region's plan to join its national power networks together.
The APG could bolster energy security, expand cross-border electricity trade, make it easier to add renewable power and help the region keep pace with rising demand.
The catch is that developers often have to spend heavily on technical studies and reserve cable-manufacturing slots years before they have the permits, commercial contracts and financing needed to move forward. Few investors and lenders are willing to absorb that early-stage risk. As a result, projects that could succeed are delayed or shelved indefinitely.
Long-distance undersea interconnectors depend on high-voltage direct current (HVDC) cables, specialised laying vessels and converters, along with surveys, permits and engineering work. Demand for this equipment and these services is climbing. Offshore wind and interconnection schemes around the world are straining a supply chain dominated by a handful of manufacturers, many of which already have orders stretching years ahead.
A project can have policy backing and willing financiers and still fail to secure a production slot. Suppliers look for credible demand, a clear procurement timeline, firm arrangements for buying the electricity, a predictable regulatory pathway and sponsors who can cover upfront costs. Without those signals, projects can wait for years or lose their place to more advanced projects elsewhere.
Energy demand in Southeast Asia is forecast to nearly triple by 2050, fuelled by industrial growth, digitalisation, electrification and rising living standards. By trading power across borders, the APG could help countries meet that demand, improve energy security, integrate renewables and reduce overall system costs.
Why HVDC cables are essential
Subsea HVDC cables will be a cornerstone of this vision. Of the 18 interconnector projects identified under the ASEAN Interconnection Masterplan Study III, five involve undersea cables. More opportunities exist along routes linking Cambodia, Indonesia, Peninsular Malaysia and Sarawak, the Philippines and Vietnam. Our research and analysis suggest the region may need at least 12 gigawatts (GW) of subsea interconnection capacity, covering more than 4,000 kilometres, by 2040 to support its power trade goals.
Singapore's goal of importing around 6 GW of low-carbon electricity by 2035 is a strong signal of demand. Reaching it will require several subsea links that connect renewable energy sources to the city-state.
The central question is who carries the early risk. Cable suppliers often ask for reservation fees or deposits years before a project reaches a final investment decision. The gap between reserving manufacturing capacity and commissioning the cable can stretch to roughly five years.
Booking deposits can amount to as much as 20 per cent of the cable contract's value, and marine surveys and engineering design also need funding early on. These outlays may be required before anyone has decided to proceed, at a time when a project could still be postponed, redesigned or cancelled. Without a way to spread this risk, sponsors may forfeit their production slots or face expensive delays.
No single sponsor can shoulder all of this early risk alone. Regional connectivity brings benefits to many countries, which gives governments, regional institutions and development partners a shared reason to help bear that risk.
Three ways to move projects forward
- Align rules and technical requirements. Harmonising approaches to planning, data sharing, cost-benefit analysis, technical standards, environmental reviews, cybersecurity and marine surveys could reduce uncertainty and make projects easier to develop.
- Coordinate demand for cable capacity. Project sponsors or several countries could pool their needs through joint tenders or shared procurement, giving suppliers a clearer view of the pipeline. Framework agreements and pre-qualified supplier panels are other workable options. In Europe, for instance, TenneT signed framework agreements covering about 7,000 km of HVDC cable for its 2 GW programme.
- Support early commitments. Suppliers consulted for our research recommended setting up a facility to absorb early-stage financial risks in APG projects, including supplier booking deposits. Such a facility would help projects secure critical manufacturing capacity and move closer to a final investment decision.
This idea could build on the Regional Connectivity Fund for Energy in Southeast Asia Trust Fund, which was launched under the ASEAN Infrastructure Fund in April 2026. The trust fund provides grants for certain project preparation work, such as feasibility studies and engineering design.
The success of the APG will depend on sharing the financial risk of securing scarce cable-manufacturing capacity before projects become bankable in the conventional sense. Governments, project sponsors, development finance institutions and other financing partners will need mechanisms that help viable projects manage this early exposure and advance toward a final investment decision.